* wait 10-15 min | * wait 10-15 min | ||
- | ==== After (brief) | + | ==== After power failure |
* reset chiller complaining about closed outlet | * reset chiller complaining about closed outlet | ||
+ | * (on-off HT breaker at the back of power supply unit) | ||
* press (longer) " | * press (longer) " | ||
+ | * (Lenses on - front of the microscope) | ||
+ | * (EDX detector controller on-off, while SIP is not running (ACD on)) | ||
* watch vacuum | * watch vacuum | ||
+ | * (HT conditioning: | ||
* HT -> Auto HT & Emission -> Start up | * HT -> Auto HT & Emission -> Start up | ||